How should a 40 to 60 m yacht run planned maintenance and running hours?

On a yacht this size a small engine department looks after a lot of machinery, much of it working hard in season, with the yard period as the only long stop. A planned maintenance system is how the work stays ahead of the machinery, and how you show a surveyor that it did.

Jordon Booth, founder of Kodo Yachts and ex-yacht crew · Updated 29 October 2026

In short: run one plan that lists every machine, gives each job an interval by the calendar, by running hours or by whichever comes first, and records every job done with the date, the hours, who did it and who signed it. Keep running hours read on a fixed rhythm, keep defects and postponements on record with their reasons, and count critical spares, so a surveyor can trace any machine's history in minutes. If class surveys the machinery under an approved planned maintenance scheme, IACS UR Z20 is the reference it works from.

At a glance

QuestionShort answer
Kinds of intervalThe calendar, running hours, or whichever comes first. Some equipment counts uses, such as starts or lifts.
The unit of workA job card: what to do, the steps, readings with limits, the parts, and a signature.
Running hoursRead on a fixed rhythm. A lower or impossible reading is explained, never overwritten.
Late workPostponed on record with the reason and who agreed. Class and statutory jobs need class's or the flag's agreement.
Critical equipmentIdentified, with standby tests and critical spares aboard (ISM Code 10.3).
Class referenceIACS UR Z20 (Rev.1 July 2018), planned maintenance scheme for machinery.

What a planned maintenance system is

A planned maintenance system (PMS) has three parts: a list of every machine and system aboard, each with a way to identify it; a plan that says what work each one needs and how often; and a record of every job done. The plan keeps the work ahead of the machinery. The record is what proves it, to the owner, the next chief engineer, a buyer's surveyor and class.

Section 10 of the ISM Code asks the company to maintain the ship in line with the rules and its own requirements: inspections at appropriate intervals, non-conformities reported with their possible cause, corrective action taken, and records kept. On a commercial yacht the PMS is how that is done. If your yacht is under 500 GT, see running a safety management system under 500 GT for where maintenance sits in the wider system.

Calendar or running hours

Every job needs an interval, and choosing the right kind matters more than the number.

IntervalUse it forFor example
CalendarThings that age or fall due whether used or notSafety equipment servicing, items tied to a survey or certificate, seasonal checks
Running hoursMachinery that wears with use, where the maker gives hoursMain engines, generators, watermakers, compressors
Whichever comes firstMachinery with hours from the maker and a time limit for when it runs littleAn engine service at the maker's hours, or after a set number of months if the engine has barely run
UsesEquipment that wears per operation rather than per hourCrane lifts, tender launches, engine starts
Date on the itemItems that carry their own expiryFlares, hydrostatic releases, batteries

Two details catch yachts out. First, decide whether each job's next date counts from the day it was done or stays on its original anniversary. A statutory or class job usually keeps its anniversary, so a late service does not quietly push the next one back. Second, a reminder that comes up early is not extra time: a job past its due point is overdue.

Running hours a surveyor will trust

A running-hours plan is only as good as its readings.

  • Read the meters on a fixed rhythm, for example with the daily engine-room round, so jobs fall due on real hours rather than last month's estimate.
  • When a meter is replaced, record the old meter's last reading and the new one's first, so the machine keeps its lifetime hours and the jobs do not jump.
  • A reading lower than the last one, or more hours than time has passed, is a mistake or a meter change. Do not overwrite it silently; write down what happened.
  • Know which machines have not been read lately. A stale reading makes an hours job look further away than it is.

Job cards and the record of work

A job card turns the maker's manual into the steps the crew follow aboard: what to do, the readings to take with their limits, the parts needed, and whether a risk assessment or a permit to work comes first. The completed card is the record. For each job done, keep:

  • the date, and the machine's running hours at the time
  • what was done and what was found, including any reading outside its limits
  • the parts used
  • who did the work and who signed for it (a contractor's work still needs someone aboard to sign)
  • any later correction, kept beside the original rather than written over it

Work on critical machinery, class items and jobs required by a rule is worth a second check, by the chief engineer or the captain, before it counts as done.

Defects, postponements and overdue work

Unplanned work belongs in the same system. A defect is raised against the machine it affects, repaired, and checked by someone other than the person who repaired it before the machine goes back into service. If the yacht has to run with a limit meanwhile (a pump not to be relied on, a generator kept off line), write the limit down with what keeps her safe until it is lifted.

When a planned job cannot be done on time (parts not aboard, on charter, waiting for the yard), postpone it on record: the original due date, the new one, the reason, what keeps the yacht safe meanwhile, and who agreed. A job required by class or a statutory rule needs the class society's or the flag's agreement, and its reference belongs with the job. A row of overdue jobs with no explanation is hard to defend in front of a surveyor.

Spares and critical equipment

Section 10.3 of the ISM Code asks the company to identify equipment whose sudden failure could lead to a hazardous situation, and to take specific measures for its reliability, including regular tests of standby arrangements and of equipment not in continuous use. In the PMS that means:

  • a list of critical equipment, with why each item is critical
  • a regular standby test for each item on the plan, or a written reason it needs none (for example because it runs continuously and is watched)
  • a minimum number of critical spares aboard, counted, with each part used recorded against the job it went on

What a surveyor wants to see

  • The equipment list, with each item identifiable aboard
  • The plan, with intervals that follow the maker's recommendations, or a recorded reason where they differ
  • Any machine's history on request: jobs done, hours at each service, defects and repairs
  • Overdue and postponed jobs, each with its reason and who agreed
  • Running hours that are current
  • Critical equipment, its standby tests and its spares
  • The makers' manuals aboard for the machinery

Where class surveys the machinery under an approved planned maintenance scheme, IACS UR Z20 (Rev.1 July 2018) is the unified requirement class societies work from for a machinery PMS; ask your class society what it needs from yours. For the requirements clause by clause, see planned maintenance and Kodo.

This page is practical guidance, not class or legal advice. Your class surveyor, your flag and your DPA have the final word on what your yacht needs.

How Kodo handles it

From the Kodo user manual for version 2.0.0:

M/Y Seafarer · MaintenanceDemo yacht
Kodo's planned maintenance on M/Y Seafarer: 29 jobs due this month, none overdue, 14 due this week, filtered by department, each with how often it repeats and when it was last done
  • The plan. Each line repeats by the calendar (real calendar months), by days, by running hours, by whichever comes first, by uses such as starts, launches or lifts, or once. A job can keep its fixed due date or count from the day it was done. There is no grace period: a job past its due point is overdue. Only the chief engineer, the master, or someone the chief engineer authorises changes the machinery lines.
  • Running hours. Every reading is kept with where it came from. A lower reading needs a reason, and from anyone other than the chief engineer, the captain, an officer or a head of department it waits for review. A meter change keeps the machine's lifetime hours, a machine not read lately shows as stale, and an hours job shows the date it is likely due from the last 30 days of use. The daily round of readings can be saved without a signal.
  • Job cards come from standard jobs kept in versions, with steps, readings with limits, calibrated instruments, and a risk assessment or permit where one is needed. A job cannot be marked done until its card is finished.
  • The record of work keeps who did the work apart from who signed it, with the running hours, parts and cost. A correction keeps the original beside it. Work on critical machines, class items and jobs that cite a rule waits for a second person to approve it.
  • Postponements. A routine job's due date is moved with a reason on record. A critical, class or rule-based job needs a postponement decided by the office, or by the master where there is no management company, and a class or rule-based one also needs the class society's or the flag's reference. The original due date stays beside the new one.
  • Defects are verified by someone other than the person who repaired them. A machine goes back into service only on the chief engineer's or the master's decision, and only the master lifts a restriction.
  • Spares and critical equipment. Stock changes only through recorded movements, and a part used on a job is recorded against it. Kodo shows critical spares below their minimum, each critical machine's standby test and when it is due, and the reviews of the critical list.
  • For class and the surveyor. Each machine has a history page that downloads as a PDF, a data file or a spreadsheet. The class page keeps the survey cycle and credits, prepares the annual report to class as a PDF, and records the surveyor's annual review.

What it does not do: Kodo is not a class-approved planned maintenance scheme and holds no class, flag or IMO approval. A surveyor has no login of their own and works from the PDFs and exports. The plan itself needs a signal to change. Coming from another maintenance system? Send us what you can export and we move it across with you; old records stay marked as legacy records and are never shown as signed in Kodo. More on the maintenance page.

Sources

Questions

Should maintenance be scheduled by running hours or by the calendar?

Both. Machinery that wears with use, such as main engines, generators and watermakers, follows the maker's interval in running hours, usually with a time limit for when it sits idle. Equipment that ages or falls due whether used or not, such as safety equipment and anything tied to a survey, follows the calendar. Where both apply, the job falls due at whichever comes first.

What does a surveyor want to see in a planned maintenance system?

A list of the machinery with a clear way to identify each item, the plan with its intervals, and a record of each job done with the date, the running hours, what was found and who signed it. Expect questions about overdue and postponed jobs, open defects, critical equipment and its standby tests, and spares for critical machinery.

Is IACS UR Z20 mandatory for yachts?

No. IACS UR Z20 sets out what class societies require when they approve a planned maintenance scheme for machinery, so it matters if you want class to credit machinery surveys on the strength of your own records. Machinery outside an approved scheme is surveyed by class in the usual way, and the ISM Code still asks for maintenance and records (section 10). Ask your class society what it needs.

What happens when a maintenance job cannot be done on time?

Record it as postponed, not quietly moved: the original due date, the new one, the reason, what keeps the yacht safe meanwhile and who agreed. A job required by class or a statutory rule needs the class society's or the flag's agreement, and its reference belongs with the job.

Is Kodo a class-approved planned maintenance system?

No. Kodo Yachts keeps the plan, running hours, job records, defects, postponements, spares and the annual report to class, but it holds no class approval as a planned maintenance scheme, and no flag or IMO approval. Your class society decides how your machinery is surveyed.